Notes for Figure 9L and 9M
NOTE 1: Connect the UPS’ green and yellow neutral-to-ground (neutral-to-earth) wire (N-G bond) to the UPS
output terminal indicated.
NOTE 2: See Table 11 on page 25 for maximum output current ratings.
* See Section 304, step 5, for instructions on setting the Output Voltage Reference parameter.
303 Installing the Overcurrent Protection Devices
1. Install the UPS input circuit breaker at the service panel. See Table 6 on page 8 and your instal-
lation wiring diagram.
2. Install the UPS output overcurrent protection device at the UPS output. See Table 7 on page 9
and your installation wiring diagram.
3. Install the load current circuit breakers or fuses.
• The load current per phase (leg) must not exceed the value listed in Table 11.
• Size per local code requirements.